- Home
- Departments
- Engineering
- Projects
- 1st Avenue & I-80 Interchange
1st Avenue & I-80 Interchange
Diverging Diamond Interchange
The Iowa Department of Transportation is reconstructing the interchange at I-80 exit 242 and 1st Avenue with a diverging diamond interchange (DDI). The Iowa DOT is the lead agency on this project.
Contact Us
-
Iowa Department of Transportation
Catherine Cutler
Transportation Planner
EmailCity of Coralville
Scott Larson
City Engineer
Email1512 7th St.
P.O. Box 5127
Coralville, IA 52241Ph: 319.248.1720
Fx: 319.248.1894
Staff Directory
Updates: Current & Upcoming Work
Major construction started in March 2023. 1st Avenue is reduced to one lane in each direction over I-80 into fall 2024. Drivers should anticipate traffic delays and plan accordingly.
- 1st Avenue
On 1st Avenue: Northbound & Southbound (Between 9th Street and Holiday Road):
November 14, 2023-Fall 2024*: - Northbound and southbound traffic shifts to the east side of 1st Avenue across I-80 and is one lane in each direction (head-to-head).
- On the south side of the interchange, pavement markings will be adjusted to improve lane assignments for northbound and southbound 1st Avenue drivers.
- 1st Avenue: Northbound (approaching E. 9th Street)
November 14-mid April 2024*: - Northbound 1st Avenue approaching E. 9th Street will have only one thru lane. The other thru lane becomes a dedicated right turn lane onto E. 9th Street.
- Once northbound 1st Avenue drivers reach the new bridge over I-80, 1st Avenue will widen to provide a separate left turn lane onto the westbound I-80 on ramp and a through lane to continue north on 1st Avenue.
- 1st Avenue: Southbound (approaching I-80):
Starting November 14, 2023*: - Southbound traffic on 1st Avenue will now be able to turn left onto the eastbound I-80 on ramp.
- On the north side of the interchange, the dedicated southbound 1st Avenue right turn lane to the westbound I-80 on ramp will be moved adjacent to the southbound 1st Avenue through lane. Drivers will turn right at the traffic signal to head west on I-80.
- Interstate 80
I-80 Eastbound Off-Ramp: to 1st Avenue Northbound (Exit 242)
November 14-December 11, 2023: - Due to the elevation difference between old and new 1st Avenue on the south side of the interchange, eastbound I-80 off-ramp traffic approaching 1st Avenue will not be able to turn left onto northbound 1st Avenue. That movement will be detoured east on I-80 to Exit 244 (Dubuque St), and back west on I-80 to 1st Avenue.
- I-80 Eastbound Off-Ramp: to 1st Avenue Northbound or Southbound (Exit 242)
December 11, 2023-mid April 2024: - Exiting I-80 eastbound traffic will be shifted to the new exit ramp and will be able to turn left and right to go northbound or southbound on 1st Avenue.
- The I-80 on ramp will continue to be where it is today until construction is completed on the new on ramp.
- I-80 Eastbound (Exit 242)*:
March 6-December 31, 2023: - Intermittent lane closures overnight between 7:00 pm and 6:00 am Monday through Thursday, and between 9:00 pm and 6:00 am Sunday.
- I-80 Westbound (Exit 242)*:
March 6-December 31, 2023*: - Intermittent lane closures overnight between 7:00 pm and 6:00 am Monday through Thursday, and between 9:00 pm and 6:00 am Sunday.
- Bicyclists & Pedestrians
Starting November 10, 2023*: - Bicyclists and pedestrians will use the new trail alignment along the east side of 1st Avenue.
- The trail goes from the northeast corner of E. 9th Street, through two new trail tunnels, over the new trail bridge, along the east side of 1st Avenue to the River Products/Hotel intersection, and to the west side of 1st Avenue via a pedestrian crosswalk signal.
- The existing trail along the west side of 1st Avenue between E. 9th Street and the Hotel entrance will be removed with the next phase of interchange reconstruction.
*(Dates subject to change based on weather and unforeseen circumstances)
**(There will be intermittent closures and detours throughout the construction season which will be communicated prior to the closures)
Comment: Davenport RCE (800-262-5145)
Please check 511ia.org for the latest updates to the project.
I-80 Eastbound to 1st Ave Northbound (effective Nov. 14, 2023)
Traffic Movements (effective Nov. 14, 2023)
Drone Images
The drone images below were captured by IDOT.
October 17, 2023
October 17, 2023
October 17, 2023
May 30, 2023
May 30, 2023
Project at a Glance
The existing interchange at I-80 exit 242 is the original configuration constructed in the 1960s when I-80 was built through Iowa. The new diverging diamond interchange will provide safety improvements and is designed to handle projected traffic volumes.
Major construction began in mid-March 2023, and reduces 1st Avenue to one lane in each direction over I-80. 1st Avenue will remain one lane in each direction over I-80 into fall 2024.
The prime contractor is Peterson Contractors, Inc., of Reinbeck, Iowa. The Iowa DOT is administering and inspecting the project.
Highlights Once Complete
- Diverging diamond interchange design eliminates the left turn phase at signalized intersections. This reduces overall traffic delay while also providing a significant safety improvement since left-turning traffic is no longer crossing opposing traffic lanes.
- New grade-separated trail with underpasses and a trail bridge over I-80.
- New 1st Avenue bridges accommodate the potential future widening of I-80.
- New, signalized intersection to serve Iowa River Landing Place and the Magellan Terminal.
- New stormwater management practices, traffic signals, roadway lighting, and aesthetic treatments.
Traffic & Pedestrian Impact
- The project will utilize staged construction, including temporary pavement and temporary traffic signals.
- One lane of traffic will be maintained in each direction on 1st Avenue at all times.
- Drivers should anticipate traffic delays and plan accordingly.
- After the 1st Avenue Trail closures in October and November 2022, pedestrian access along 1st Avenue over I-80 should not be impacted again for the remainder of the project.
Timeline
- September 2022: DOT letting.
- October 24-28 and November 7-11, 2022: Two trail closures of the 1st Avenue Trail where it crosses I-80. The trail closures allow for construction of temporary pavement in preparation for the start of major construction in spring 2023.
- October 24-November 18, 2022: Intermittent lane closures on 1st Avenue, one direction at a time.
- Starting in late March/early April 2023: Major construction work begins with the demolition and reconstruction of the easterly (northbound) 1st Avenue bridge over I-80. 1st Avenue traffic is reduced to one lane in each direction, with northbound traffic shifted onto the westerly (southbound) 1st Avenue bridge. 1st Avenue remains one lane in each direction into fall 2024.
- Fall 2023: 1st Avenue traffic shifts onto the east side of 1st Avenue across I-80 so demolition of the west side can begin. 1st Avenue remains one lane in each direction over I-80 into fall 2024. Pedestrians and bicyclists begin to use the new trail alignment across I-80 along the east side of 1st Avenue.
- By spring/summer 2025: The road and bridge work is expected to be substantially complete.
- Summer/fall 2025: Final landscaping and related work should be complete.
Funding
The project is funded in part by a $20 million U.S. Department of Transportation BUILD grant awarded to the City of Coralville and transferred to Iowa DOT, with the remaining costs covered by the Iowa DOT.
The bid from Peterson Contractors Inc. was $35.6 million.
Learn More
Iowa Department of Transportation
Iowa DOT project website
Watch Video: Navigating the Diverging Diamond Interchange
Stay Informed
- Check 511ia.org for the latest updates to the project
- Sign up for e-news alerts ("Construction and Traffic Updates" category)
- Like City of Coralville, Iowa on Facebook
- Follow the City of Coralville, Iowa on Twitter
- Join Nextdoor (a private social network for Coralville neighborhoods)
-
1st Ave & I-80 Interchange Project: Traffic Control Change Starts on December 4
A change in traffic control on 1st Avenue at I-80 starts on December 4, and continues until mid-April 2024 Read on... -
Johnson County Hazard Mitigation Plan Kick-Off Meeting
Johnson County EMA invited the public to attend on Monday, December 7, at 7:00 pm via Zoom Read on...
-
1st Ave & I-80 Interchange Project: Traffic Control Change Starts November 14
A change in traffic control on 1st Avenue at I-80 starts November 14, and continues until mid-December 2023 Read on...