Clear Creek Trail - Phases 6 & 7

Clear Creek Trail to Extend to Tiffin


The Clear Creek Trail currently runs south of Highway 6 along Clear Creek for 4.3 miles. The trail will be extended an additional 1.9 miles from east of Deer Creek Road to Creekside Ballpark, then on to connect with Tiffin's Clear Creek Trail west of I-380.

Highlights


After work is complete, the 1.9 mile section of trail will feature:
  • 10' wide paved trail
  • Two bridge crossings over Clear Creek
  • Multiple crossings under interstate bridges
  • Connection to Tiffin's Clear Creek Trail

Cost


  • Received $1,112,600 in federal funds
  • Bid in January 2018
  • Low bid: $1,758,552.84 (Iowa Bridge and Culvert of Washington, Iowa)

Timeline


  • Start: March 2018
  • Estimated completion: Fall 2018
  • Estimated trail opening: Late 2018, but future trail closures related to the I-80/I-380 interchange construction will be necessary
Clear Creek Trail sign

Contact Us

  1. Dan Holderness


    City Engineer
    Email

    Scott Larson


    Assistant City Engineer
    Email

    1512 7th St.
    P.O. Box 5127
    Coralville, IA  52241

    Ph: 319.248.1720
    Fx: 319.248.1894

    Staff Directory

Updates*


  • Most of the bridge east of Deer Creek Road is expected to be complete in mid-June. Once complete, grading will begin for all of the trail length south of I-80.
  • Paving south of I-80 is expected to be complete in July.
  • The trail connection to Creekside Ballpark is expected to open in late summer 2018 and will open as soon as it is safe to do so.
  • Trail work north of I-80 involves another bridge over Clear Creek, a 10’ x 10’ box culvert across a large drainage channel, and work associated with crossing under multiple I-80 and I-380 bridges.  
  • Once the trail opens, the trail segment between I-80 and I-380 will be closed on a temporary basis due to the I-80/I-380 interchange project. View the trail alignment relative to the interchange project limits (PDF).  
*Updated June 8, 2018